Protection System Testing, commissioning & Trouble Shooting of Faults:
-
Protection Testing increases reliability of electrical power system after installation of the system
-
Problems are rectified before live commissioning of the grid station/ equipment
-
Base line values are obtained for future comparison of routine annual testing
-
Correct installation of equipment, interface wiring checks are applied and testing of relays & control system is carried out to establish proper installation & control wiring
-
Lastly function tests of the whole system are carried out
-
IT& C has sufficient experienced protection testing staff having vast experience in 500 KV, 220 KV & 132 KV grid stations.
-
Testing equipment is available to carry out the tests
-
Our team is fully equipped to rectify faults existing electrical system and testing of relays under live conditions.